CCP問題数、CCP実際試験

 

NO.1 The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side
of your split screen., using the drop down menu, to reference during your response/choice of
responses.
What is the range of unit costs?
A. $485.00
B. $26.65
C. $21.57
D. $48.22
Answer: A

CCP初心者

NO.2 Meetings require:
A. Goals, an agenda, preparation, control, good listening skills and relevant discussions
B. Goals, an agenda, flipchart, computer projector, laser pointer and consulting with others where
appropriate
C. Goals, an agenda, preparation, relevant discussions, support for your actions and to consider the
total physical and human setting of the meeting
D. Goals, an agenda, preparation, conclusions, control and conversations that are relevant
Answer: D

NO.3 A major theme park is expanding the existing facility over a five-year period. The design phase
will be completed one year after the contract is awarded. Major engineering drawings will be
finalized two years after the design contract is awarded and construction will begin three years after
the award of the design contract. New, unique ride technology will be used and an estimate will need
to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side
of your split screen, using the drop down menu, to reference during your response/choice of
responses.
Why is a +/- notation necessary when developing an estimate?
A. It is a government requirement
B. Contingency cushion
C. There are unknowns that affect the final cost of a project
D. It makes up for the lack of time to develop a real estimate
Answer: C

CCPガイド CCP攻略

NO.4 A major theme park is expanding the existing facility over a five-year period. The design phase
will be completed one year after the contract is awarded. Major engineering drawings will be
finalized two years after the design contract is awarded and construction will begin three years after
the award of the design contract. New, unique ride technology will be used and an estimate will need
to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side
of your split screen, using the drop down menu, to reference during your response/choice of
responses.
Select the statement that best describes the method to estimate the cost of the new rides:
A. Call vendors for quotes
B. Break down the technology into components
C. Use historical data from past projects
D. Adjust known data from existing rides
Answer: D

CCP問題集無料 CCP vue

君は一回だけでAACE InternationalのCCP問題数に合格したいなら、或いは自分のIT技能を増強したいなら、JapanCertはあなたにとって最高な選択です。長年の努力を通じて、JapanCertのAACE InternationalのCCP問題数の合格率が100パーセントになっていました。うちのAACE InternationalのCCP問題数は完全な無制限のダンプが含まれているから、使ったら気楽に試験に合格することができます。

JapanCertは専門的に IT認証試験に関する資料を提供するサイトで、100パーセントの合格率を保証できます。それもほとんどの受験生はJapanCertを選んだ理由です。JapanCertはいつまでも受験生のニーズに注目していて、できるだけ皆様のニーズを満たします。 JapanCertのAACE InternationalのCCP問題数は今までがないIT認証のトレーニング資料ですから、JapanCertを利用したら、あなたのキャリアは順調に進むことができるようになります。

試験番号:CCP 問題
試験科目:「Certified Cost Professional (CCP) Exam」
最近更新時間:2016-10-13
問題と解答:115